GeezerVison is showing github.com — task(cluster): install and verify the dedicated 20A circuits · Issue #1105 · developing-today/code
task(cluster): install and verify the dedicated 20A circuits #1105Labels area/infraInfrastructure, deployment, and operationseffort/lLarge: multi-day or open-ended; expect staged check-insepic/lab-clusterEpic: lab-cluster - all issues of this effort carry itmeta/enrichedIntake review done: acceptance criteria, links, and normalized labels addedmode/physicalNeeds physical hands on site: build, install, cable, or configure devicesstatus/needs-triageNot yet triaged; needs a first lookuser/ownedA user is personally driving this; automation stays out DescriptionInstall and verify the dedicated 20a circuits
Parent epic: #1083 (basement cluster program). Project home: planning/roadmaps/basement-cluster.md.
The install itself (electrician, Drew on site): dedicated runs per spec, breakers labeled, outlets tested under load with the first machines. No agent does electrical work - this issue tracks the visit and its verification.
Acceptance: circuits live and labeled; load test results and photos attached; panel schedule updated.
Physical work notes
- Location: basement / server room, Osseo WI.
- Tools/parts: as listed in the task; note anything missing on this issue before starting.
- Safety: machines unplugged before drive or cable work; circuits are electrician-only work (epic 3).
- Verification: attach a photo of the finished state (and SMART/KVM output where relevant) to this issue before closing.
Activityadded user/ownedA user is personally driving this; automation stays out area/infraInfrastructure, deployment, and operations effort/lLarge: multi-day or open-ended; expect staged check-ins meta/enrichedIntake review done: acceptance criteria, links, and normalized labels added mode/physicalNeeds physical hands on site: build, install, cable, or configure devices on Oct 27, 2026developing-today commented on Oct 27, 2026 dezren39 commented on Nov 5, 2026 Scope update — Drew, 2026-11-04 ~23:33 CST
This ticket remains the execution ticket for the electrician goal (goal_55d3136785c6, basement electrician: dedicated 20A circuits for server room) under epic #1083. Tonight Drew refined the scope; the install/verify core below stands, with these additions:
Checklist
- Select + engage an electrician (quote step first). No candidate is recorded in the goal workspace yet — first quote request goes out from the existing spec: the electrician brief written 2026-10-29 (fleet task 2998, PR docs(cluster): electrician brief — circuit spec for the basement cluster (#1103) #2367) specifies 4 dedicated 20A circuits, a 600W/machine planning assumption, 1920W derated per circuit, and site-visit open items. Update that brief with this scope before sending.
- Review of the current home breaker panel: capacity, free breaker spaces, and a load calculation for the lab at full build-out — ~12 cluster machines + 2–3 mini PCs + the Dell switches (at the brief's 600W/machine planning assumption, machines alone are ~7–9 kW).
- Check the existing wiring on the lab circuits: condition and gauge adequacy for 20A runs (the ceiling run past ~3 unfinished walls from the GOAL spec; existing cable paths may be reusable).
- Install between 4 and 16 dedicated breakers/circuits routed into the home lab, preferably 20A each. The count is a range on purpose: the panel review + load calculation above decide where in 4–16 we land (the prior brief said 4; full build-out may justify more). Record the decided count + reasoning on this ticket.
- Label every new breaker and lab outlet run (matches the build-out set's physical labeling pass).
- Verification: each circuit tested under load; the circuit → what-it-feeds list recorded on this ticket; panel schedule updated (already in acceptance below).
Dependency (both ways)
Power is the gate for the home lab build-out set — epic #6066 (racking #6070, Dell switches #6073/#6074/#6075, cluster interconnect, TALM/Talos bring-up). Heavy racking sequences after or alongside this electrical work, not before the circuits it plugs into exist. Conversely, the final circuit count depends on the build-out's full machine list, which #6066 tracks.
Location: home lab, 13113 7th St, Osseo WI. Electrician-only work; Drew on site.
MetadataMetadataarea/infraInfrastructure, deployment, and operationseffort/lLarge: multi-day or open-ended; expect staged check-insepic/lab-clusterEpic: lab-cluster - all issues of this effort carry itmeta/enrichedIntake review done: acceptance criteria, links, and normalized labels addedmode/physicalNeeds physical hands on site: build, install, cable, or configure devicesstatus/needs-triageNot yet triaged; needs a first lookuser/ownedA user is personally driving this; automation stays out DevelopmentNo branches or pull requestsIssue actions
|