GeezerVison is showing github.com — pm-stack: make Project #4 auditable — scheduled export of fields, views, item counts, status/area distribution · Issue #1218 · developing-today/code
pm-stack: make Project #4 auditable — scheduled export of fields, views, item counts, status/area distribution #1218DescriptionPart of epic #1184 (PM stack coherence review, 2026-10-26).
Project #4 is unauditable with normal tooling. Evidence: the sandbox gh token lacks read:project scope, so Project fields/views/counts cannot be enumerated directly, and there is no committed export or snapshot. The only machine-readable copy rides inside the fleet feed via a siloed collector token, and that pipeline has already failed silently once (PR #992: projects section omitted under the systemd unit).
Acceptance:
- An auditor with only repo access can state Project Bump build/buck/preludes/buck2-prelude from
3a02ea3 to 9530656 #4's fields, views, total items and counts by Status/Area/repo from an artifact <=24h old.
- An empty or absent projects section raises a visible signal (empty-section alarm) instead of silently omitting.
- The export is scheduled/recurring, not a one-off snapshot.
Acceptance criteria
- An auditor with only repo access can state Project Bump build/buck/preludes/buck2-prelude from
3a02ea3 to 9530656 #4's fields, views, total items, and counts by Status/Area/repo from an artifact ≤24h old.
- An empty or absent projects section raises a visible signal (empty-section alarm) instead of silently omitting.
- The export is scheduled/recurring, not a one-off snapshot.
Activitydeveloping-today commented on Oct 27, 2026 dezren39 commented on Oct 28, 2026 Intake review
Related: epic #1184; PR #992 is the cited silent-failure precedent (projects section omitted under the systemd unit). Siblings #1220 (coverage report) and #1226 (Needs-Drew queue) both consume this export.
Notes: the sandbox gh token lacks read:project scope (per the body), so the export must ride the collector-token pipeline that already feeds the fleet feed — the alarm half is as important as the export half. No merged PR references this issue (checked this run).
Risks: another silent omission is the exact failure being fixed; land the empty-section alarm with or before the export.
Suggested approach: add the scheduled export beside the existing projects collector, plus a section-presence check in the aggregator that surfaces loudly.
🤖 Agent note · filed
- Agent: fleet monitor
- Session / ID: repo-fleet-monitor run 2026-10-28 02:19 CDT
- Found via: monitor reconciliation
- Task: Intake enrichment (protocol §5): acceptance-criteria section appended, labels normalized, this review posted.
- Expectation: effort as labelled; done when the acceptance criteria above are met.
developing-today commented on Nov 7, 2026
Progress from repo-worker-code-g: revalidated: PR #3995 open, implementing #1218; reviewing PR for merge developing-today commented on Nov 7, 2026
Progress from repo-worker-code-g: PR #3995 conflicts resolved in worktree (9 hunks, unions + snapshot loop reconciled to main pagination tests); targeted 100/100 pass; full-suite baseline comparison running developing-today commented on Nov 7, 2026
Progress from repo-worker-code-g: PR #3995 merge-resolved + verified (targeted 100/100, full-suite fails subset of main baseline, tsc clean); merging PR developing-today commented on Nov 7, 2026 🤖 Agent note · done
- Agent: queue worker (repo-worker-code), lane code-g — FALLBACK MODE (queue backend down, code#6619)
- Task: triage of issue pm-stack: make Project #4 auditable — scheduled export of fields, views, item counts, status/area distribution #1218 → remaining work was the already-open implementation PR pm-stack: publish auditable Project #4 snapshot (#1218) #3995, stale and conflicting since 2026-11-01.
- What this shift did: resolved PR pm-stack: publish auditable Project #4 snapshot (#1218) #3995's merge conflicts against current main in a laptop worktree (9 hunks across feed.ts, projects.ts, server.ts, watchdog.ts, sources/live.ts, projects.test.ts — additive unions, plus reconciling the PR's fetchProjectSnapshot loop with main's pagination contract: 10-page truncation error message restored, completeness guard scoped to shortfalls). Merge commit on the PR branch: 524575f.
- Verification (laptop): targeted suites projects+feed+watchdog 100/100 pass; full aggregator suite failures are a strict subset of the clean-main baseline failures (pre-existing/load flake, zero regressions);
bunx tsc --noEmit clean after bun install.
- Outcome: PR pm-stack: publish auditable Project #4 snapshot (#1218) #3995 MERGED 2026-11-07T04:44:14Z, merge commit 5243d05. Project Bump build/buck/preludes/buck2-prelude from
3a02ea3 to 9530656 #4 fields/views/total + Status/Area/repo distributions now ride the scheduled (5-minute) fleet-feed collector, gated by isProjectAudit, with absent/empty/stale watchdog diagnoses — all three acceptance criteria are implemented on main. Closing issue pm-stack: make Project #4 auditable — scheduled export of fields, views, item counts, status/area distribution #1218.
developing-today commented on Nov 7, 2026
Released by repo-worker-code-g (outcome: done). PR #3995 merged 5243d05 (conflict resolution 524575f by lane code-g; targeted tests 100/100, full-suite fails subset of clean-main baseline, tsc clean). Project #4 audit snapshot + watchdog alarms on main; issue #1218 closed. developing-today commented on Nov 7, 2026 🤖 Agent note · CORRECTION + fix-forward (lane code-g)
MetadataMetadataDevelopmentNo branches or pull requestsIssue actions
|