GeezerVison is showing github.com — pm stack: multi-board hierarchy + full task genealogy · Issue #9060 · developing-today/code
pm stack: multi-board hierarchy + full task genealogy #9060Todo 11 / 1211 of 12 issues completedTodo 11 / 1211 of 12 issues completed Descriptionpm stack: multi-board hierarchy + full task genealogy
Starter epic for Drew's directive of 2026-11-12 (~16:27 CST). This epic owns the
program end to end: design first (Phase 1), then data side (Phase 2), then
dashboard surfaces (Phase 3). Implementation slices are filed as native
sub-issues of this epic as the design lands.
The requirement (Drew, in substance)
The PM stack must support many boards, with boards as siblings or
parent/children of each other, forming one navigable hierarchy:
-
Overall high-level roadmap → per-project roadmaps → per-project designs and
epic-level items → a granular current-implementation / WIP board.
-
Every task has parents up to the top, relayed through epics, milestones,
and labels. The canonical genealogy statement the stack must be able to
produce for any item:
"We are working on bugfix X as part of epic Y, which was spawned by
design Z; epic Y is part of larger project roadmap item A, which exists
as part of the overall system's second active roadmap priority CC, which
was started after C closed with the release on <date>."
-
Milestones are release containers: a milestone closes with a release and
carries close-out accounting — the counts of issues, designs, and epics it
covered (the shape Drew gave: a milestone that closed with a release
covering 123 issues, 23 designs, and 4 epics).
-
Epics can carry over across milestones. A carryover epic may be larger
in scope than the closed child epics under the milestone it carried over
from — it holds fixes from already-merged work plus the later phases of a
large design.
-
Designs spawn designs. A large design can spawn further designs (Drew's
example: 5 spawned — 2 done, 2 in progress, 1 blocking the final design's
start). The blocking relation must be representable and visible.
-
Close rules: a larger epic and its project roadmap item close when
(a) its designs are all done, AND (b) its medium/high-priority bugs and
follow-ups are closed. Whatever is still unfinished at that point is
re-parented — to the most-related epic, or to the project's general
maintenance epic.
-
Primary parent: moved issues keep all their labels, but the most
important parent must be marked — an extra label or a metadata section in
the issue/PR description (Drew's two candidate shapes). At minimum this
must exist in the PM stack; in GitHub too if feasible. The design phase
picks the canonical form.
Substrate already in place (build on it, do not redo)
- Native sub-issue chains + epic/design label families in this repo; taxonomy
and current lineage in pm-stack/lineage-manifest-2026-11-12.md (PR pm-stack: lineage manifest 2026-11-12 — epic/board/label register #8980,
merged).
- Boards: developing-today Project Bump build/buck/preludes/buck2-prelude from
3a02ea3 to 9530656 #4 (1,229 items, Area/Status fields, view
Update Rust crate clap to 4.3.11 #22 "ID Program"), developing-today Project Bump build/buck/preludes/buck2-prelude from 3a02ea3 to 370cd4d #5 (Idea Register),
developing-today-forks Project test #1, Clustered-Computing "Lab Cluster"
Project test #1.
- Design register machinery: epic Design register 2026-11-11: every Drew-asked design Sep 28–Nov 11, tracked in the PM stack #8805 +
pm-stack/design-tracking-manifest-2026-11-11.md.
project-reconcile.sh — the board's single-writer sync, now on fleet gh
(token rotation), all count caps removed by Drew's 2026-11-12 ruling.
- The 2026-10-26 visualization design (impl(aggregator+collector): complexity-weighted project visualization (rollup, hands queue, blocked weight, depth graph) #1122): native sub-issue edges +
blockedBy via the collector's GraphQL, effective-Area inheritance.
Phases
- Phase 1 — design. A design note under
doc/ (repo convention) defining:
(a) the board registry model (boards as data: org, project number, role —
overall/project/wip — parent board, sibling order) so the collector is
multi-board by configuration; (b) hierarchy levels + edge types (native
sub-issue parent, spawned-by design→epic, epic→roadmap-item,
roadmap-item→roadmap-priority, blocked-by) and where each edge lives;
(c) milestones as release containers with close-out accounting + carryover
semantics; (d) the primary-parent convention — canonical form, exact
format, re-parenting behavior on close, and a maintenance epic per project;
(e) the genealogy read model — ancestor-chain computation + sentence
rendering + the dashboard surfaces. Implementation slices filed as
sub-issues with acceptance criteria.
- Phase 2 — data side. Collector multi-board by registry (all current
boards), hierarchy edges ingested, primary-parent implemented in the
collector + backfilled over today's epics/chains (worked example: the
crate-split chain — steps → pkgs/id: split the monolith crate into sub-crates along module seams (prioritized by Drew 2026-11-01) #3447 → pkgs/id: build-time review — runtime performance first, then build time (cold check build ~16 min, tests run 12 s) #3195 → epic: ID platform expansion — apps, comms, currency, hosting, boards (2026-10-28 directive, LIST 6–15) #2056, designs linked),
milestone/release accounting computed from existing milestones. Aggregator
redeployed; the projects API serves boards + chains; the canonical
genealogy example verified end-to-end on real data.
- Phase 3 — dashboard. Overall roadmap view, per-project roadmap views,
genealogy header (the sentence) on item pages, milestone close-out
summaries.
Acceptance (program level)
- Design note merged; implementation slices filed as sub-issues.
- Collector serves all current boards from a registry (no hardcoded
single project), with hierarchy edges.
- The canonical genealogy sentence renders from real data for a real
item, end to end.
- Milestone close-out accounting (issues/designs/epics counts) computed
for existing milestones.
- Primary-parent marks exist on the backfilled chains (crate-split chain
as worked example).
- Dashboard shows overall roadmap, per-project roadmap, and the
genealogy header — or Phase 3 remains as filed issues with the design
merged, reported exactly as such.
Links
Phase status (2026-11-12)
- Phase 0 — intake: DONE. This epic is filed with labels epic, app/pm-stack, epic/pm-stack. Native parenting under the PM-stack coherence epic epic(dashboard): PM stack coherence - single-URL, fresh data, triage-able, hierarchical #1184 was attempted and is blocked by GitHub's 100-sub-issue-per-parent cap (epic(dashboard): PM stack coherence - single-URL, fresh data, triage-able, hierarchical #1184 is full — API 422). Cross-linked by comment instead; the design (§2) records the cap as a substrate constraint with the intermediate-grouping-epic rule.
- Phase 1 — design: DONE. Design note merged to main via PR doc: PM stack multi-board hierarchy + full task genealogy design (#9060) #9064 (merge 673bb40):
doc/2026-11-12T22-50-00Z_design_pm-board-hierarchy-genealogy/note.md (27,629 B), including the 16:45 amendment sections 11–16.
- Phase 2/3 — implementation: FILED as the 12 native sub-issues below. The collector multi-board + per-org identity slice is the pre-filed pm-stack collector: multi-project pool (forks + lab boards) and App-bucket identity #9062 (this design is its specification).
Amendment absorption (Drew, 2026-11-12 16:45 CST)
- Link semantics → design §11 + slice impl(pm-stack): primary-parent convention + historical link semantics + crate-split backfill #9066. Links are records (relation + status active/historical/removed + since/until/reason): one direct parent at a time; splits retain the old parent as historical; misclassifications are removed (auditable removal, never blurred with history). Level-agnostic; board→board links use the same record shape.
- Metadata section in every issue/PR → design §12 + slices impl(pm-stack): primary-parent convention + historical link semantics + crate-split backfill #9066/impl(fleet): fleet gh Metadata superset — create-path stamping + DB insert (extends #9016) #9073. Delimited
<!-- pm-metadata:start/end --> block containing a JSON dictionary (JSON chosen over YAML: strict parse, native in both fleet/Rust and the TS collector; arbitrary keys, nested values). Canonical home of direct_parent, links[], lineage fields, provenance. GitHub-native marks remain the GitHub-side representation; reconcile keeps them in agreement and reports divergence.
- fleet gh superset → design §13 + slice impl(fleet): fleet gh Metadata superset — create-path stamping + DB insert (extends #9016) #9073 (extends fleet gh step 2: higher-level sync tools on the token rotation #9016). Create parses existing Metadata, stamps queue id / scheduled start / now / pwd / worktree / host / pickup + work-start times / lane-start issue set / session id / model, enforces required fields, pushes, then inserts the full record into the DB itself. Metadata query features → slice impl(fleet): metadata database + fleet Metadata query surface #9074.
- Session state → design §14 + slice impl(fleet): session state — session id in env + worktree pwd-file #9075. Session id assigned per fleet start; stored in env AND a pwd-file at every operated worktree's root; resolution order explicit arg > env > pwd-file.
- Database → design §15 + slice impl(fleet): metadata database + fleet Metadata query surface #9074. Every issue/PR in scope; full Metadata as JSON + extracted key fields indexed; first-class query surface alongside GitHub; bodies win on content, divergence is a healing target.
- Dual ingestion / self-healing → design §16 + slice impl(fleet): dual ingestion — webhook listener + interval sweeper, Metadata backfill, retroactive completion #9076. Webhook listener + interval sweeper; missing Metadata ascertained/generated/stored (+ written back where fleet has access); insufficient cases forwarded to full triage; quickly-merged PRs completed retroactively.
Slice map (native sub-issues of this epic)
- pm-stack collector: multi-project pool (forks + lab boards) and App-bucket identity #9062 — collector: board registry + multi-board + per-org identity (pre-filed; design = its spec)
- impl(pm-stack): satellite board field-schema standardization (forks #1, Lab Cluster #1) #9065 — satellite board field-schema standardization (forks test #1, Lab Cluster test #1)
- impl(pm-stack): primary-parent convention + historical link semantics + crate-split backfill #9066 — primary-parent convention + historical link semantics + crate-split backfill
- impl(pm-stack): release milestones — convention, ingestion, close-out accounting #9067 — release milestones: convention, ingestion, close-out accounting
- impl(pm-stack): design-spawn backfill — native parenting of sub-design tracking issues + spawn rollup #9068 — design-spawn backfill + spawn rollup
- impl(pm-stack): per-project maintenance epics + closure gate + re-parent tooling #9069 — per-project maintenance epics + closure gate + re-parent tooling
- impl(pm-stack): genealogy read model — ancestors, spawned-by, sentence renderer, API #9070 — genealogy read model: ancestors, spawned-by, sentence renderer, API
- impl(pm-stack): dashboard surfaces — genealogy header, per-project roadmap, overall priorities, releases #9071 — dashboard surfaces: genealogy header, per-project roadmap, overall priorities, releases
- impl(fleet): fleet gh Metadata superset — create-path stamping + DB insert (extends #9016) #9073 — fleet gh Metadata superset: create-path stamping + DB insert (extends fleet gh step 2: higher-level sync tools on the token rotation #9016)
- impl(fleet): metadata database + fleet Metadata query surface #9074 — metadata database + fleet Metadata query surface
- impl(fleet): session state — session id in env + worktree pwd-file #9075 — session state: session id in env + worktree pwd-file
- impl(fleet): dual ingestion — webhook listener + interval sweeper, Metadata backfill, retroactive completion #9076 — dual ingestion: webhook listener + interval sweeper, backfill, retroactive completion
Cross-links: #9016 (step-2 sync tools — the fleet-superset slices extend its scope), #9062 (above), #8805 (design register), #1122 (visualization design), lineage manifest PR #8980. Sub-issuesCollapse Sub-issuesSub-issues11 of 1211 of 12 Issues completedLoading 12 sub-issues Activitydeveloping-today commented on Nov 12, 2026 dezren39 commented on Nov 23, 2026
Released by felix (outcome: free). Triage complete (record comment 7105573753): epic not resolved/superseded; legs 1-4 met, leg 6 met-in-fact (#9071 landed, awaiting close), leg 5 blocked on #9066 (project-reconcile.sh has no in-repo implementation). Resume: re-triage when #9066 unblocks/closes or #9065/#9071 close. dezren39 commented on Nov 23, 2026 Triage record — lane oc-code-02, 2026-11-23 (task 18814). Verified fresh against origin/main ab82a4d76c0 and live slice states. Verdict: not resolved, not superseded; the program epic remains open, 5 of 6 acceptance legs now formally met, leg 5 unblocked-in-fact and routed back to its slice.
Since the prior triage record (comment 7105573753, lane felix, 15:26Z), two slices moved:
Acceptance legs against current main:
- Design note merged + slices filed — MET (PR doc: PM stack multi-board hierarchy + full task genealogy design (#9060) #9064, merge 673bb40).
- Collector serves all current boards from a registry with hierarchy edges — MET (pm-stack collector: multi-project pool (forks + lab boards) and App-bucket identity #9062 CLOSED status:done; impl(pm-stack): satellite board field-schema standardization (forks #1, Lab Cluster #1) #9065 CLOSED status:done).
- Canonical genealogy sentence renders end-to-end — MET (impl(pm-stack): genealogy read model — ancestors, spawned-by, sentence renderer, API #9070 CLOSED status:done).
- Milestone close-out accounting — MET (impl(pm-stack): release milestones — convention, ingestion, close-out accounting #9067 CLOSED status:done).
- Primary-parent marks on backfilled chains — NOT MET, but no longer blocked: impl(pm-stack): primary-parent convention + historical link semantics + crate-split backfill #9066 OPEN status/blocked; its recorded blocker (task 20430,
packet_defect: project-reconcile.sh has no implementation in this repo) is now satisfied in fact by the hosted reconcile path. PR impl(fleet-hosted): sync-tool verbs — project sync + queue/GitHub sync endpoints (#12591) #12935 (issue impl(fleet-hosted): sync-tool verbs — project sync + queue/GitHub sync endpoints (#9016 hosted) #12591, merged 2026-11-23T05:22:06Z) lands POST /v1/sync/project with the script's own outbox op names, server-side id resolution and already-applied retries (pkgs/fleet/hosted-worker/src/sync.ts, src/routes/sync.ts); fleet gh step 2.1: Project sync verb on the token rotation (project-reconcile caller set) #10972 records that this is the in-repo successor to project-reconcile.sh's caller. The missing script is therefore no longer a blocker — impl(pm-stack): primary-parent convention + historical link semantics + crate-split backfill #9066's reconcile leg is satisfiable against the in-repo sync endpoint. The unchanged, still-unimplemented part of impl(pm-stack): primary-parent convention + historical link semantics + crate-split backfill #9066 is the primary-parent label convention, collector validation and the crate-split backfill.
- Dashboard surfaces — MET (impl(pm-stack): dashboard surfaces — genealogy header, per-project roadmap, overall priorities, releases #9071 CLOSED status:done; PRs pm-stack: add roadmap priorities and release surfaces #12073/fix(pm-stack): preserve program timeline notes #12079 merged, live-verified 2026-11-20).
Remaining slices: #9066 (OPEN, being unblocked and requeued — this comment is its unblock evidence), #9068 (OPEN status/parked — native-parent backfill blocked on #1184's 100-child cap plus unmapped F3/F4/P2 parents; its own recorded resume condition), #9073 (OPEN status:in-review — slices 10–12 remain its own remainder).
Routed follow-on: task 20430 unblocked with this evidence so #9066 resumes as real implementation work (labels + collector validation + reconcile-via-/v1/sync/project + crate-split backfill with readback). No code changed by this triage.
Resume condition for this epic triage: re-triage when #9066 closes, or when #9068/#9073 close. dezren39 commented on Nov 23, 2026
🤖 Agent note — triage (task 21447, lane oc-code-05, 2026-11-23T20:12Z)
Verdict: unchanged — the triage record above (comment 7107626…, lane oc-code-02, task 18814, 19:47Z) is current. This task is a duplicate intake of the same issue filed 14 minutes after that record; no re-verdict is needed and no follow-on packet is filed.
Fresh checks this run: #9060 OPEN, no hold labels. All twelve slices unchanged since 19:47Z — #9062/#9065/#9067/#9069/#9070/#9071/#9074/#9075/#9076 CLOSED; #9066 OPEN (status/triaged, unblock note posted 19:48Z), #9068 OPEN (status/parked), #9073 OPEN (status:in-review). Implementation task 20430 (#9066) was claimed at 19:48:59Z and is live in lane code-i with the resume brief intact — the epic's leg 5 is now owned implementation work, not a triage question.
Resume condition: re-triage this epic when #9066 closes, or when #9068/#9073 close. dezren39 commented on Nov 23, 2026
Triage, lane code-h (task 21447), 2026-11-23, fresh state read.
Verdict: not resolved and not superseded. The epic stays open. This is a duplicate intake of the triage already recorded by lane oc-code-02 (task 18814, 19:47Z), so no new packet is routed.
Live sub-issue state: open are #9066 (primary-parent convention, blocked on project-reconcile.sh having no in-repo implementation), #9068 (design-spawn backfill), and #9073 (fleet gh Metadata superset). The other nine sub-issues are closed. developing-today-fleet commented on Nov 26, 2026 ContributorAuthor More actions
Triage verdict — code-j, 2026-11-26 (queue task 24345)
Fresh check: #9060 OPEN, labels queue/queued + epic + app/pm-stack + status:to-do + epic/pm-stack. Not resolved, not superseded — program epic with 2 of 12 slices still open:
Verdict: epic stays open; every open slice holds a live task, so no new packet is routed — a duplicate would repeat 24344/20271. Resume: re-triage when #9066 closes or #9068 unblocks/closes. No code changed in this pass. developing-today-fleet commented on Nov 26, 2026 ContributorAuthor More actions
Duplicate-intake triage (code-h, task 24489, 2026-11-26): no new verdict. Code-j triage task 24345 (2 min prior) is current and verified fresh: #9066 OPEN, #9068 OPEN, #9073 CLOSED. Epic stays open; no packet routed from this intake. developing-today commented on Nov 27, 2026 Fresh re-triage (task #25237, 2026-11-27): the parent is still open and not superseded. #9066 is now CLOSED as implemented; #9073 was already closed; the only remaining child slice is #9068, still OPEN/parked with live task #20271 and the recorded capacity/mapping resume condition. PR #15100 is an open conformance test for #12833/#9074, not a closure of the outstanding #9068 acceptance. The epic remains a valid umbrella; I created no duplicate child task and blocked this parent disposition on #9068 until that child progresses.
MetadataMetadataDevelopmentNo branches or pull requestsIssue actions
|