GeezerVison is showing github.com — dashboard: Phase tracker panel (Phases 0–13 + validation #1075–#1078) for the id section (#1239 split) · Issue #9923 · developing-today/code
dashboard: Phase tracker panel (Phases 0–13 + validation #1075–#1078) for the id section (#1239 split) #9923DescriptionSplit from #1239 by the task 15180 fresh triage (2026-11-14, lane any-c). Parent: #1239 (dashboard: full id platform coverage).
Work
Build the Phase tracker panel in the aggregator's id section:
Acceptance
Activitydeveloping-today commented on Nov 14, 2026 dezren39 commented on Nov 14, 2026
Picked up by repo-worker-code-b — working this now. (Fleet queue fallback mode: the queue backend is down, so this issue's comments carry the claim. The claim stays live while repo-worker-code-b posts progress markers; after 30 minutes of silence any other worker may pick this up.) dezren39 commented on Nov 14, 2026
Progress from repo-worker-code-b: verified: archaeology - F-item mapping sources are heterogeneous plan prose; checking every phase source before deciding build vs spec dezren39 commented on Nov 14, 2026 agent-note:v1 — archaeology complete, mapping gap named; released for a build session (lane code-b, FALLBACK MODE backend down, 2026-11-14)
Claimed and investigated the Phase tracker panel. Verdict: the validation half is buildable today; the per-phase F-item progress half is not, because the F-item mapping the issue presupposes does not exist in any uniform machine-readable source. Building it anyway would mean inventing a mapping — exactly the hand-maintained input this panel forbids. Findings, all verified fresh against main this shift:
The mapping gap (the real gate):
.opencode/plans/phase-11-foundations.md — the only plan with a parseable F-item list: - **F11.n Name (#nnn).** list items (F11.1 Nix CI cannot read the relay kit from the repo-root doc tree #238, F11.2 Stabilize shared-state failures in Firefox E2E CI #229, F11.3 Bulk LogSync test retries a mid-stream reset instead of explaining it #241, F11.4 id(ci): F11.4 fast CI lane under 15 minutes #551, …).
.opencode/plans/phase-12-platform-flexibility.md — 28 F12. mentions in prose; the clean F12 mapping actually lives in planning/roadmaps/id.md table cells (F12.11 #805, F12.12 #557, …) and in id: Path to Phase 12 — ordered prerequisite queue (CI trust → validation → journal → visibility → remaining F11) #1235's Tier-2 line (F12.1 id: F12.1 apply wiring — module install + schedules reconciliation #807 … F12.18 id(world): F12.18 denial-of-service test suite in CI #560).
.opencode/plans/phase-9-portable-platform.md — zero F9. items; no F-numbering at all.
.opencode/plans/phase-13-client-shells.md — F13 refs are inline prose mentions (F13.2, F13.4–F13.8), not a task list; the roadmap records only F13.1 id: Phase 13 F13.1 versioned shell contract (client-server frame spec + conformance check) #783 / F13.2 id: Phase 13 F13.2 SSH as a transport for the frame protocol (id world join --via ssh) #784 as done.
- Phases 0–8 and 10 — no F-item plan found anywhere (
.opencode/plans/, planning/, doc/ searched); Phase 8 has only a design-items doc.
Buildable now (the validation slice): #1075 (Phases 0–8 + platform completion), #1076 (Phase 9), #1077 (Phase 10), #1078 (delivered Phase 11) — all four verified CLOSED today, titles carry the phase mapping, and their states resolve through the aggregator's existing items source. A panel section rendering phases 0–11 validation state from those four refs (reopened follow-up changes it live) needs no new data source. Wiring mirrors the just-merged #9922 panel (PR #10060): a section in renderProgramProject for config id, states from the items map, source timestamp + stale honesty.
Build order for the next session: (1) validation slice above, with the reopened-issue fixture case; (2) Phase 11 progress from the phase-11 plan list + Phase 12 progress from the roadmap table / #1235 Tier-2 refs, each parsed with fixture tests; (3) Phases 0–10 + 13 progress only after a phase-mapping source of record exists — the honest way to create one is a phases table in planning/roadmaps/id.md (maintained as plan data, parsed like the repo-roadmap source already parses those tables), NOT a mapping hardcoded in the aggregator. Until (3)'s source exists, those phases render validation state + "no F-item mapping source" instead of a fabricated percentage.
Released free with this spec; nothing built, no PR opened. dezren39 commented on Nov 14, 2026
Progress from repo-worker-code-b: archaeology complete: F-item mapping gap named on issue with build order; releasing free for a build session dezren39 commented on Nov 14, 2026
Released by repo-worker-code-b (outcome: free). Archaeology complete, nothing built: no uniform machine-readable F-item mapping exists for Phases 0-13 (only phase-11 plan list, phase-12 roadmap table/#1235 Tier-2; phase-9 plan has no F-items; phases 0-8/10 have no plan). Validation slice (#1075-#1078, all CLOSED, phase mapping in titles) is buildable now; full build order + the phases-table source-of-record proposal recorded on #9923. dezren39 commented on Nov 14, 2026
Agent note — validation slice MERGED; remainder parked with build order intact (task 16681, lane any-c, 2026-11-14)
Delivered (build-order step 1): the Phase tracker panel on the id program page — per-phase validation state for Phases 0–13 derived live from the aggregator's GitHub items. The four #796 audits map by their own titles (#1075 → Phases 0–8, #1076 → 9, #1077 → 10, #1078 → 11; all already in the id project's tracked refs, so no source/config changes were needed). Closed audit → validated; reopened audit → validation-open for exactly its phases; unresolved audit renders as unresolved; open follow-ups referencing an audit surface on its phases; Phases 12–13 render "no validation audit". Pure derivation in src/phase-tracker.ts (the #9922 pattern), panel composed beside Path to Phase 12. Tests: 6 new fixture tests incl. the reopened-validation-issue case; full aggregator suite compared against a pristine-main baseline run the same way — zero branch-only failures (the suite's reds are pre-existing on main, cf. #9529).
Environment note for the next worker: running bun test inside a ~/git/fleet/* worktree on the laptop produces spurious failures — bun cannot resolve web-push from its global cache under that path, so subprocess-spawning tests exit 1 and boot tests time out. The identical tree under /tmp is clean. Work in a /tmp worktree (or the main checkout) for aggregator test evidence; CI is unaffected.
Remainder (parked, in build order):
2. Phase 11 progress from the .opencode/plans/phase-11-foundations.md F-item list + Phase 12 progress from the planning/roadmaps/id.md table / #1235 Tier-2 refs, each parsed with fixture tests (pattern: src/phase12.ts parsers).
3. Phases 0–10 + 13 progress — gated on a phase-mapping source of record (proposed: a phases table in planning/roadmaps/id.md, maintained as plan data and parsed like the repo-roadmap source). Until it exists, those phases correctly render validation state only.
Task 16681 is parked with this remainder; the issue stays open. dezren39 commented on Nov 14, 2026
Agent note — step 2 MERGED (Phase 12 progress); remainder parked (task 16681, lane code-a, 2026-11-14)
Delivered (build-order step 2, Phase 12 half): the Phase tracker panel now shows Phase 12 progress — derivePhase12Progress counts the ordered steps in #1235's body (parsed/joined by phase12.ts) against live GhItem state: done iff the step's issue is closed live (a checked step whose issue reopened counts as open); absent/stale/step-less feeds withhold the percentage. Panel gained a Progress column; other phases state the gap instead of inventing a number. Tests: 4 new fixture tests; phase-tracker suite 10/10, phase12 suite green; full aggregator suite matches pre-existing main reds (a11y table-semantics A/B-identical on pristine main; cf. #9529). Codex review could not run — usage limits, retried once at 17:11Z, same limit — so there were no findings to disposition; merged on test evidence with that fact recorded on PR #10285.
Phase 11 half of step 2 — not derivable as specified, with the evidence: the step text assumed the F11 list parses like #1235's checklist. It does not: in .opencode/plans/phase-11-foundations.md only F11.1 (#238), F11.2 (#229), and F11.3 (#241) carry an issue ref in the item header; the other 15 items' refs are prose-level and ambiguous (F11.11 names #250 for a done part and #242 for an open part). A header join would fabricate progress for 15 of 18 items, which the panel's no-invented-values rule forbids. This finding is also recorded in the phase-tracker.ts header on main.
Remainder (parked, in build order):
3. Create the phase-mapping source of record (proposed: a phases table in planning/roadmaps/id.md, maintained as plan data and parsed like the repo-roadmap source) covering F-item → issue mappings for Phases 0–11 and 13 — including a researched F11 mapping for all 18 items — then derive progress for those phases exactly as Phase 12 now does. Until it exists, those phases correctly render validation state only.
Task 16681 is parked with this remainder; the issue stays open. dezren39 commented on Nov 14, 2026
state: done (fixed_merged — build order complete)
task: 16681 (lane any-d, repo-worker-code)
PR: #10321 — MERGED 2026-11-14T18:08:19Z (merge 9f17133)
Delivered (build-order step 3, the last remaining step): the phase-mapping source of record + derived progress for Phases 11 and 13.
planning/roadmaps/id.md gained the "Phase tracker — F-item mapping" table, researched and verified against live GitHub today: Phase 11 F11.1–F11.18 — dedicated F-item issues (Nix CI cannot read the relay kit from the repo-root doc tree #238, Stabilize shared-state failures in Firefox E2E CI #229, Bulk LogSync test retries a mid-stream reset instead of explaining it #241, id(ci): F11.4 fast CI lane under 15 minutes #551, id(world): F11.5 injected Clock for the world actor and scheduler #552, id(world): F11.7 host metrics, Prometheus endpoint and tracing spans #553, id(ci): F11.8 benchmark harness with committed baselines #539, id(world): F11.9 bytes-per-frame baseline table #542, id(world): F11.10 split world.rs, world_session.rs and cli.rs (moves only) #540, id(world): F11.11 enforce the client projection with a structural test #543, id(world): F11.13 error taxonomy: stable codes plus reasons on the wire #554, id(roc): F11.15 smaller example modules (wasm-opt -Os, strip, <=400 KB) #555, id(world): F11.16 replay self-check (id world verify) #544, id(world): F11.17 a trapping view must not poison the world #547, id(roc): F11.18 pin the Roc compiler for checked-in example modules and rebuild them in CI #541), F11.12 → Define rollback compatibility for world profile journal entries #227, and the two PR-delivered items F11.6 → PR feat(id): measure per-call guest fuel and guard it with budgets #247 / F11.14 → PR fix(id): make territory's view fit eight seats within the default fuel #248 (per the 2026-10-20 status record; no dedicated issues exist for them). Phase 13 F13.1–F13.8 → id: Phase 13 F13.1 versioned shell contract (client-server frame spec + conformance check) #783–id: Phase 13 F13.8 multi-server, multi-client topology; client-only mode always supported #790 in order (5 closed, 3 open → the panel now shows 5/8 for Phase 13; Phase 11 derives 18/18 from live states).
- New pure module
pm-stack/aggregator/src/phase-mapping.ts (parser + derivation; oracle = the Phase 12 one: done iff the mapped ref is closed/merged in live state; a live kind mismatch counts unresolved, never done), optional Source.phaseMapping() served by the live source from the code checkout (5-min cache, fail-soft), server-side ref resolution into the items map, and the panel renders mapped progress beside the id: Path to Phase 12 — ordered prerequisite queue (CI trust → validation → journal → visibility → remaining F11) #1235 Phase 12 count. Phases 0–10 keep the stated gap — their plans have no F-item numbering, so there is nothing honest to count.
- Tests: 5 new fixture tests in test/phase-mapping.test.ts (including one asserting the real roadmap file carries the full mapping); targeted suites 29/29; full aggregator suite failure set identical to a pristine-main baseline (zero branch-only failures); tsc clean in touched files. Codex review failed on usage limits with no findings produced and CodeRabbit was rate-limited — disposition recorded on PR feat(aggregator): Phase tracker F-item mapping source of record (#9923 step 3) #10321 (comment 6881965819), same as sibling PRs feat(aggregator): plan views — baseline ratios, column sorting, dominance hides (#9852 items 1-3) #10127/feat(aggregator): Phase tracker Phase 12 progress from #1235 steps (#9923 step 2) #10285/feat(aggregator): provider multi-select for the Model Explorer (#9852 item 4) #10291.
With steps 1 (PR #10122), 2 (PR #10285), and 3 (this PR) all merged, the #9923 build order is complete and this issue closes. Reopen if a future plan gives Phases 0–10 F-item numbering — the mapping table is the only edit needed for the panel to pick it up.
MetadataMetadataDevelopmentNo branches or pull requestsIssue actions
|